News Articles
Culvert Construction Update
Posted on Aug 6th, 2011
During the week of August 8th, the construction work on the East Caley Avenue Improvements Project at Goldsmith Gulch will include pouring the concrete drainage pan in the channel to connect to the existing pan, the concrete sidewalks and curb along East Caley Avenue, asphalt paving/patching and striping of East Caley Avenue, Xcel electric line relocation and site restoration. The site restoration work will be coordinated with each of the property owners (HOAs) to ensure that identified items are completed prior to acceptance of the project.
SEMSWA appreciates your cooperation and if you have any questions you are welcome to send them to the project manager, Molly Trujillo at mtrujillo@semswa.org or call SEMSWA’s main number (303) 858-8844.